Adjustments

<< Click to Display Table of Contents >>

Navigation:  Oil and Gas Production (OGP) > Production Utilities > WolfePak Pumper Import > WPPumper Basic Operations >

Adjustments

Adjustments

This will be accessed from the Lease on each of the tabs. Below is an example from the Tank Reading Tab.

Pumper Adj 1

 

It is important to know that the production for the day of the adjustment will be recalculated and the result could be negative or out of tolerance production. Click Edit to make changes to an existing Adjustment. Click New to add a new Adjustment.

Pumper Adj 2

Tank

If New was selected from Daily Entry the tank will default to the tank selected on the page. Otherwise, one will need to be selected.

Adjustment Date

Will default to the current processing date. It can be changed if needed. It cannot be in the future.

Adjustment Type

Must be selected from the drop down.

Adjustment Barrels

Cannot be zero. This value can be either positive or negative. A positive value will be added to the production calculated. A negative value will reduce the production calculated. Most adjustments will be a positive value (tank leak, BW&W circulation, water pull, etc.).

Notes

Enter any notes. The notes field will have a default value after the Adjustment Type is selected.